SUTOR Global has successfully completed the replacement of the EKO I and II system – the so-called economizers – in the Trmice heating plant.
The work took place from mid-June to the end of July and it was our first replacement of an EKO of this size within the CEZ Group – a technically and logistically demanding project that we managed ahead of schedule.
Key figures:
- 2 new EKO (8 chambers and 210 snakes)
- 900 assembly welds
- 24-hour shifts, 7 days a week