For many, insulation is merely synonymous with boring foam and endless kilometers of sheet metal. At SUTOR Global, however, we understand that every insulation project presents a unique challenge – especially when it involves technically demanding equipment such as the TG27 turbine in Komořany.
Between November 2024 and February 2025, our team successfully completed a comprehensive insulation project for our valued partner, Doosan Škoda Power. The project was not just about insulating the turbine itself – our work encompassed a complete solution from project documentation to final cladding.
Key aspects of the implementation included:
- Complete project documentation for insulation.
- Supply and installation of insulation and cladding for the turbine, valve RZ, valve chamber, piping systems, fittings, and special equipment.
- Turnkey implementation, including complete scaffolding provision.
An average of 15 experienced professionals participated in the project, ensuring that everything was completed on time and to a high standard.
We thank the entire SUTOR Global team for their professionalism and commitment, and Doosan Škoda Power for their trust in the successful implementation. We are already looking forward to the next challenges in the field of insulation.